Effects of tunnelling on existing support systems of perpendicularly crossing tunnels

journal contribution
posted on 2023-05-17, 02:32 authored by Hongyuan LiuHongyuan Liu, Small, JC, Carter, JP, Williams, DJ
The interactions between perpendicularly crossing tunnels in the Sydney region are investigated using a full three-dimensional (3D) finite element analysis coupled with elasto-plastic material models. Special attention is paid to the effect of subsequent tunnelling on the support system, i.e. the shotcrete lining and rock bolts, of the existing tunnel. The results of the analysis show that in a region such as Sydney, with relatively high horizontal stresses, installation of the new tunnel causes the shotcrete lining of the existing tunnel to be in tension in the side facing towards the tunnel opening and in compression at the crown and invert. The pre-stressed rock bolts are usually tensioned more in the sections closest to the tunnel opening. For this particular study, if a new tunnel is driven perpendicularly beneath an existing tunnel, significant increases are induced in the bending moments in the shotcrete lining at the lateral sides of the existing tunnel and in the axial forces at its crown and invert. The increase in side bending moments causes further tensile cracking but the crown and invert stresses remain within the thresholds for both compressive failure and tensile cracking for shotcrete lining of typical concrete quality. Moreover, the driving of the new tunnel causes the tensile forces in the existing side rock bolts to increase and those in the existing crown rock bolts to decrease. In contrast, if the new tunnel is driven perpendicularly above the existing tunnel, compressive failure of the existing shotcrete lining is induced at the crown of the deeper tunnel for concrete of typical capacity and a significant tensile force increase of the existing rock bolts around the crown. It is concluded that in order to ensure the stability of the existing tunnel, local thickening is needed at the sides of the existing shotcrete lining if the shallow tunnel is installed first and local thickening is needed at the crown if the deep tunnel is installed first. © 2009 Elsevier Ltd. All rights reserved.

History

Publication title

Computers and Geotechnics

Volume

36

Issue

5

Pagination

880-894

ISSN

0266-352X

Department/School

School of Engineering

Publisher

Elsevier Sci Ltd

Place of publication

The Boulevard, Langford Lane, Kidlington, Oxford, England, Oxon, Ox5 1Gb

Repository Status

  • Restricted

Socio-economic Objectives

Civil construction processes

Usage metrics

    University Of Tasmania

    Exports

    RefWorks
    BibTeX
    Ref. manager
    Endnote
    DataCite
    NLM
    DC